ROPP FACTORY ACCEPTANCE TEST CHECKLIST This blank checklist structures a project-specific ROPP capping trial. It does not set universal pass values. Acceptance criteria must be approved for the actual bottle, closure, product and quality method. 1. PROJECT AND SCOPE Project / quotation reference: Customer / site: Machine model and configuration: Machine serial or build reference: Trial date and location: Responsible representatives: Approved formats included: Excluded scope: 2. PACKAGING CONTROL Bottle supplier and drawing revision: Bottle lot(s) and sample quantity: Closure supplier and drawing revision: Closure lot(s) and sample quantity: Liner / insert / pourer details: Product or trial-liquid condition: Decorative finish / scuff standard: Retained uncapped controls identified: 3. TOOLING AND FORMAT PARTS Capping head / pressure block identity: Thread-roller identity: Tuck-under / pilfer-band roller identity: Bottle support / platform identity: Guides / starwheels / transfer parts: Cap feeder / chute / transfer parts: Recorded height, pressure and setting references: Change-parts list checked and labelled: 4. LINE INTERFACES Upstream equipment and agreed bottle condition: Conveyor height, direction, speed and spacing: Cap storage, orientation, refill and low-level method: Downstream equipment and blocked-line response: Start permissives / healthy signals / fault signals: Emergency-stop boundary and restart responsibility: Reject or containment method where specified: 5. QUALITY METHODS Visual cap-height and alignment method: Thread-form and cap-finish standard: Pilfer-band / bridge / tuck-under standard: Opening method, instrument and calibration reference: Conditioning time and sample temperature: Leak / inversion / storage method: Sampling plan, including every head where applicable: Retest / quarantine / deviation rule: 6. OPERATING TESTS First-off samples approved: Stable-run condition defined: Run duration defined: Gross cycles or accepted finished bottles defined: Inspection frequency defined: Treatment of rejects and stops defined: Cap refill tested: Cap starvation / feeder interruption tested where specified: Planned stop and restart tested: Downstream blocked response tested where specified: Changeover and first-off approval tested: 7. RESULTS AND CLOSE-OUT Good bottles produced: Rejects by agreed cause category: Line stops and cause: Opening results reference: Leak results reference: Visual / tamper-band results reference: Head-by-head evidence reference: Approved samples retained and labelled: Open deviations and responsible owner: Final agreed operating window: Customer sign-off: Lancing sign-off: Date: